Brown's Point
2017 Oil House Restoration
The Oil House had been neglected for some time and so a major restoration was begun in 2016.
Before restoration
The project included:
- Abatement/removal of rusted, contaminated metal
- Installation of new metal siding and trim
- Add new replicated metal trim such as signature pieces over the door.
Restoration in progress
Restoration completed.
2019 Generator Building Restoration
The Generator Building had been neglected for some time and so a major restorations was begun.
Before restoration
The restoration included:
- Remove lead-base paint and asbestos tile flooring
- Replace existing roof
- Restore the original window frames and sashes
- Build and install security storm covers
- Replicate metal ventilation louvers
- Replace front door
- Paint exterior and interior
After restoration
New windows and louvres
New door
The work was started in 2018 and completed in February 2019.